Tasks - Prepare Working Group Revisions
Tasks - Prepare Working Group Revisions
Assigned to;
- Working Group members
Additional Participants;
- Staff Manager and Staff
Primary Deliverables;
- Working-Group revisions to the Initial Report (or, think of this as the first-draft of the Final Report)
Tasks include;
Task |
Start |
Finish |
Review and understand the Initial Report, Constituency Statements and Public Comments sections of the working-group wiki |
Sept 24 |
Sept 25 |
Conduct working sessions for each section of the draft report (the goal at this stage is to incorporate all comments) Teleconference |
Sept 26 |
Sept 26 |
Edit draft revisions (to eliminate redundancy and identify areas of non-consensus) |
Sept 27 |
Oct 2 |
Conduct consensus-building sessions (possible outcomes; consensus, defer for more information, non-consensus) Teleconference |
Oct 3 |
Oct 3 |
Complete revisions and release to the working group wiki |
Oct 4 |
Oct 8 |