12 Workplan
Translation and Transliteration of Contact Information Work Plan PDF
Amended Draft Work Plan 2 April 2015
Final Translation and Transliteration of Contact Information PDP WG Work Plan & Timeline (updated 21 February 2014)
Target Date | What | Deliverable / Topic for Discussion | Who |
19 December 2013 | T&T Meeting | - Inaugural Meeting | All |
09 January 2014 | T&T WG Meeting | - Confirmation of Co-Chairs - Overview discussion of relevant Charter questions
| All |
16 January | T&T WG Meeting | - Assess Work Plan & WG approach - Discuss SG/C Input Template & SO / AC outreach message | All |
23 January | T&T WG Meeting | - Finalise Work Plan & WG Approach - Finalise SG/C Input Template & SO/AC outreach | All |
24 January | Send out SC/C Input Template & SO/AC outreach |
| Staff |
30 January | T&T WG Meeting | - Review Charter Questions | All |
6 February | T&T WG Meeting | - Review Charter Questions | All |
13 February | T&T WG Meeting | - Review Charter Questions | All |
20 February | T&T WG Meeting | - Review Charter Questions | All |
21 February | Deadline for SG/C and SO/AC outreach (Deadline Extended to 31 March) | - Distribute SO/AC and SG/G Input Review Tool | Staff |
27 February | T&T WG Meeting | - Review Charter Questions in light of SG/C/SO/AC comments | All |
6 March | T&T WG Meeting | - Review Charter Questions in light of SG/C/SO/AC comments | All |
13 March | T&T WG Meeting | - Review Charter Questions in light of SG/C/SO/AC comments - Planning for F2F in Singapore | All |
22 March | F2F T&T WG Meeting, Singapore | - Presentation of work accomplished so far - Continue to review SG/C/SO/AC comments | All |
3 April | T&T WG Meeting | - Review of F2F Meeting - Continue review of SG/C/SO/AC comments | All |
10 April | T&T WG Meeting | - Finalizing review of SG/C/SO/AC comments | All |
17 April | T&T WG Meeting | - Finalizing review of SG/C/SO/AC comments | All |
24 April | T&T WG Meeting | - Stock Take: Where are we, what are the key issues that needs discussion - Review of relevant work that is taking place in other relevant efforts | All |
01 May | T&T WG Meeting | - Review of Work Plan | All |
08 May | T&T WG Meeting
| - Discussion on open issues & development of draft recommendations | All |
15 May | T&T WG Meeting | - Discussion on open issues & development of draft recommendations | All |
22 May | T&T WG Meeting | - Discussion on open issues & development of draft recommendations | All |
29 May | T&T WG Meeting | - Discussion on open issues & development of draft recommendations | All |
05 June | T&T WG Meeting | - Discussion on open issues & development of draft recommendations | All |
12 June | T&T WG Meeting | - Preparation for London F2F Meeting | All |
25 June | F2F WG Meeting, London | - Presentation of Work achieved so far - Discussion on open issues & development of draft recommendations | All |
3 July | T&T WG Meeting | - Discussion on open issues & development of draft recommendations | All |
10 July | T&T WG Meeting | - Discussion on open issues & development of draft recommendations | All |
17 July | T&T WG Meeting | - Continue review of comments received | All |
24 July | T&T WG Meeting | - Continue review of comments received | All |
31 July | T&T WG Meeting | - Continue review of comments received | All |
7 August | T&T WG Meeting | - Continue review of comments received | All |
14 August | T&T WG Meeting | - Continue review of comments received | All |
21 August | T&T WG Meeting | - Continue review of comments received | All |
28 August | T&T WG Meeting | - Continue deliberations on open issues identified in the Initial Report - Schedule / Work plan check point | All |
4 September | T&T WG Meeting | - Continue deliberations on open issues identified in the Initial Report
| All |
11 September | T&T WG Meeting | - Finalising and Submitting Initial Report | Staff |
12 September | Opening Public Comment | - Submitting announcement to relevant websites, mailing lists, etc. | Staff |
15 September | T&T WG Meeting | - Deadline for Initial Report to be submitted for Los Angeles ICANN Meeting | All / Staff |
25 September | T&T WG Meeting | - Preparation for Los Angeles F2F Meeting | All |
02 October | T&T WG Meeting | - Preparation for Los Angeles F2F Meeting | All |
15 October | F2F WG Meeting, Los Angeles | - Presentation of Initial Report - Discussing with Community | All |
24 October | Closing Public Comment | - Staff Prepare Public Comment Review Tool and Distributes to WG | Staff |
30 October | T&T WG Meeting | - Review of Public Comments | All |
06 November | T&T WG Meeting | - Review of Public Comments | All |
13 November | T&T WG Meeting | - Review of Public Comments | All |
20 November | T&T WG Meeting | - Review of Public Comments and Preparing Final Report | All/Staff |
27 November | T&T WG Meeting | - Review of Public Comments and Preparing Final Report | All/Staff |
01 December | Deadline to Submit Motion for 11 December GNSO Council Meeting |
|
|