Timeline for RG activities
Suggested timetable for gTLD RG during the Objection Period
Date | Activity |
---|---|
June 13 2012 | Reveal Day - start of 7 month Objection Period |
January 16 2013 | The gTLD RG seeks comments from At-Large during the Objection Period. Comments received from At-Large are added to the new gTLD Dashboard at http://bit.ly/newgtld where other members of the At-Large community can read and post further comments. |
January 18 2012 | The gTLD RG reviews the comments on the new gTLD Dashboard and for each gTLD application with At-Large comments, the gTLD RG decides whether or not to draft a formal objection statement directed to that gTLD application on either limited public interest grounds or community grounds or both. |
February 1 2013 | Where the gTLD RG determines that an objection statement is appropriate, the gTLD RG proceeds to drafting the objection statement, keeping the At-Large community informed via the gTLD Dashboard. The gTLD RG publishes final objection statements to gTLD applications in a format ready to submit to the Dispute Resolution Service Provider (DRSP). |
March 1 2013 | Each of the 5 Regional At-Large Organisations (RALOs) reviews each objection statement and decides whether it supports the filing of the objection statement by the ALAC. Each RALO sends to the ALAC its advice on the objection statements on whether the RALO supports the filing of an objection statement by the ALAC or not. |
March 2 2013 | Objection statements NOT supported by at least 3 RALOs will not be considered by the ALAC. For those objection statements that are supported by 3 or more RALOs, the ALAC decides whether to file such objection statements to the DRSP. |
March 13 2013 | end of Objection Period |
Suggested timetable for gTLD RG during the Application Comment Period
The new gTLD Review Group (gTLD RG) agreed to the revised timetable due to the ICANN Prague meeting taking a great deal of time for At-Large to submit comments
(See email to the gTLD RG list)
Date | Activity |
---|---|
June 13 | Reveal Day - start of 60 day Application Comment Period (ACP) |
until end of July 26 | get comments from At-Large on the At-Large new gTLD Applications Dashboard Workspace (this would be Figure 2 of the Procedure to submit comments on and file objections to new gTLDs ) |
July 26 - July 27 | gTLD RG would review comments on the At-Large new gTLD Applications Dashboard Workspace and decide whether to draft formal comments (this would be Figure 3 of the Procedure to submit comments on and file objections to new gTLDs ) |
July 26 - August 2 | draft of formal comment posted on At-Large new gTLD Applications Dashboard Workspace and worked on by gTLD RG (this would be Figure 4 of the Procedure to submit comments on and file objections to new gTLDs ) |
August 2 to August 10 | final comment posted by gTLD RG on August 3 for ALAC's approval (this would be Figure 5 of the Procedure to submit comments on and file objections to new gTLDs ) |
August 12 | ACP ends |