IRTP Part A - Draft Working Group Timetable
Draft – For discussion purposes only – updated following 2 September conference call
IRTP Part A - Draft Working Group Timetable
Milestone Event |
Due Date (Actual / Expected) |
Status |
Day (as in by-laws) |
Day (Actual / Expected) |
PDP Launched |
25 June 2008 |
Completed |
0 |
0 |
Working Group Formed |
5 August 2008 |
In Process |
10 |
41 |
Finalise Constituency Statement Template |
2 September 2008 |
In Process |
|
69 |
Launch of Public Comment Period on the Initiation of the PDP |
4 September 2008 |
Not Started |
0 |
71 |
Public Comment Period on the Initiation of the PDP complete |
29 September 2008 |
Not Started |
20 |
96 |
Constituency Statements to Staff Manager |
3 October 2008 |
Not Started |
35 |
100 |
Initial Report Complete |
17 October 2008 |
Not Started |
50 |
114 |
Final review of Initial Report by WG* |
28 October 2008 |
Not Started |
|
125 |
Start of Public Comment Period |
29 October 2008 |
Not Started |
50 |
126 |
Public Comment Period Complete |
9 December 2008 |
Not Started |
70 |
167 |
Final Report Complete & Submitted to GNSO Chair |
19 December 2008 |
Not Started |
80 |
177 |