Project Package
Baseline Project Plan: TPR_P1_Project_Plan_20210702.pdf
The proposed key milestone dates:
- 16 Jun 2022 – Deliver Phase 1A Initial Report on Transfer Policy for public comment, begin Phase 1B deliberations on Change of Registrant
- 14 Sep 2022 – Conclude review Phase 1A comments
- 30 Mar 2023 – Deliver Phase 1B Initial Report for public comment
- 28 Jun 2023 – Conclude review of Phase 1B public comments
- 16 Aug 2023 – Deliver Phase 1A, 1B Final Report to the GNSO Council
- Phase 2 is not in scope for this plan, but this process will be repeated when it begins.