Project Status:
Board Determination on Final Report in March 2019
Implementation ongoing/subject to prioritization- refer to the implementation page for more information.
8 September 2018 - CCT Final Report - 35 Recommendations Produced | ||||
Board Action | Approved (in full or in part*)* | Passed through to community groups (in full or in part)* ) | Pending (in full or in part*) | Rejected |
6 Board Approves Recsapproves recs. 1, 17, 21, 22, 30, and 31 | 14 Board Passes passes through Recs 9, 10, 12, 16*, 19, 20*, 25, 27, 28, 29, 32, 33, 34, and 35 | 17 Boards puts in pending Recs 6, 7, 8, 11, 13, 16*, 18, 20*, 23, 24 and 26 | 0 | |
17 Board Approves Recs approves recs 6, 7, 8, 11, 13, 16*, 18, 20*, 23, 24 and 26) | 14 | 6 | 0 | |
17 | N/A14 | 4 | 2 Boards rejects Recs 14 , and 15 | |
29 July 2024 | 17 | N/A14 | 0 | 6 Board rejects Recs 2, 3, 4 , and 5 |
*CCT Recommendations 16 and 20 were put in pending (later approved) in part and passed through to community group(s) in part, and are included in the numbering of both categories.
Background
Launched under the Affirmation of Commitments (AoC), the Competition, Consumer Trust and Consumer Choice Review Team (CCT-RT) was formed to assess the New Generic Top-Level Domain (New gTLD) Program in three areas: competition, consumer trust and consumer choice. The review also assessed the effectiveness of safeguards put in place to mitigate issues arising from the introduction of new gTLDs and the Program's application and evaluation process. The review, now contemplated under ICANN Bylaws section 4.6, examined the degree to which the process of implementing the New gTLD Program was successful in producing desired results and achieving the stated objectives.
The CCT-RT produced 35 final recommendations for Board consideration and released its CCT Final Report on 8 September 2018.
On 1 March 2019, the Board took action on each of the 35 recommendations contained in the CCT Final Report, as specified within the scorecard titled “Final CCT Recommendations: Board Action (1 March 2019)“:
- On 26 January 2020, the Board subsequently approved the plan for implementation for the 7 accepted recommendations, subject to prioritization.
See See https://www.icann.org/resources/reviews/specific-reviews/cct for more information.