Action items identified during leadership meetings & plenary calls are reported in the tables below:

OPEN ACTIONS/REQUESTS


Item #Source of RequestDate of RequestAction Item RequestAction OwnerAnticipated Completion Date
021Co-Chair Meeting #003b Deliverables Discussion | 24 OCT 202424 OCT 2024

ICANN to help develop example SOs to provide real world test cases for certain deliverables.

ICANN Org11 NOV 2024
025Plenary Meeting #003 | 28 OCT 202428 OCT 2024

Draft Work Plan and Timeline to accomplish the 12 Deliverables from the Terms of Reference within a 14 month timeframe

Co-Chairs / ICANN org

18 Nov 2024

033Plenary Meeting #004 | 18 NOV 202418 NOV 2024Draft a scope statement for discussion in the next meeting.

ICANN org

02 DEC 2024












































COMPLETED ACTIONS/REQUESTS


Item #Source of RequestDate of RequestAction Item RequestAction Owner

Anticipated Completion Date

Completed ResponseCompletion Date
001Co-Chair Meeting #001 | 20 SEP 202420 SEP 2024Email each PHR Team member to remind them of required onboarding tasks and request bios.ICANN Org23 SEP 2024Email sent to review team.23 SEP 2024
002Co-Chair Meeting #001 | 20 SEP 202420 SEP 2024

Develop a staff paper that outlines the development of the CIP and Holistic Review recommendations and discusses how the two could function together. 

ICANN Org10 OCT 2024Email with document attached sent to the team. Combined with Action Item #15.25 OCT 2024
003Co-Chair Meeting #001 | 20 SEP 202420 SEP 2024Prepare a timezone friendly schedule for co-chair and plenary calls.ICANN Org30 SEP 2024Calendar invitations sent to the team.14 OCT 2024
004Co-Chair Meeting #001 | 20 SEP 202420 SEP 2024Invite ATRT3 Shepherds to attend the second plenary call to discuss the purpose of the Holistic Review and its relationship to the CIP.ICANN Org10 OCT 2024Calendar invitation sent.08 OCT 2024
005Plenary Meeting #001 | 30 SEP 202430 SEP 2024

Create a visual of the CIP and PHR timelines to view overlapping activities. 

ICANN Org11 OCT 2024Visual created and to be shared at next plenary call. 30 SEP 2024
006Plenary Meeting #001 | 30 SEP 202430 SEP 2024

Send Doodle Poll to find preferred day of the week for recurring plenary calls (bi-weekly), and schedule accordingly.

ICANN Org04 OCT 2024Doodle poll created and link ready to send in meeting summary email. 30 SEP 2024
007Plenary Meeting #001 | 30 SEP 202430 SEP 2024See Item #004 - Invite Cheryl Langdon-Orr and Pat Kane (ATRT3 Co-Chairs) to the next plenary call as guests for a Q&A session.ICANN Org11 OCT 2024Calendar invitation sent.08 OCT 2024
008Plenary Meeting #001 | 30 SEP 202430 SEP 2024Schedule time to review the Terms of Reference as part of the next plenary call agendaICANN Org11 OCT 2024Agenda for next plenary call drafted and will be sent with the calendar invitation30 SEP 2024
009Plenary Meeting #001 | 30 SEP 202430 SEP 2024

Share ICANN81 session information for CIP/PHR.

ICANN Org11 OCT 2024ICANN81 information shared in Meeting Chat and will be sent with the meeting summary email. 30 SEP 2024
010Co-Chair Meeting #002 | 08 OCT 202408 OCT 2024

Offer the Pilot Holistic Review Team the opportunity to attend a rotating schedule for plenary calls.

ICANN Org10 OCT 2024Email sent to review team.08 OCT 2024
011Co-Chair Meeting #002 | 08 OCT 202408 OCT 2024

Send an acknowledgement of receipt email sent from an Observer to the RSA-Coordinators inbox.

ICANN Org10 OCT 2024Email sent to confirm the email was received and forwarded to the Co-Chairs. 09 OCT 2024
012Co-Chair Meeting #002 | 08 OCT 202408 OCT 2024

Send a personalized invitation to ATRT3 Co-Chairs Cheryl Langdon-Orr and Patrick Kane to attend the next plenary call.

ICANN Org10 OCT 2024Email sent to Cheryl Langdon-Orr and Patrick Kane.09 OCT 2024
013Plenary Meeting #002 | 14 OCT 202414 OCT 2024

Send out placeholder calendar invitations for the next 6 months. 

ICANN Org18 OCT 2024Calendar invitations sent to the list. 14 OCT 2024
014Plenary Meeting #002 | 14 OCT 202414 OCT 2024

Provide a link to the Terms of Reference and the team reviews prior to the next call.

ICANN Org18 OCT 2024Link sent in Chat during the meeting and in a follow-up email. 16 OCT 2024
015Plenary Meeting #002 | 14 OCT 202414 OCT 2024Summarize the dialog with the ATRT3 Co-Chairs and share with the PHR Team, remaining cognizant of non-native English speaking members as part of the meeting minutes. ICANN Org18 OCT 2024Email with document attached sent to the team. Combined with Action Item #2.25 OCT 2024
016Plenary Meeting #002 | 14 OCT 202414 OCT 2024Develop a work plan outlining how the team will conduct work both within calls and independently in-between calls.ICANN Org25 OCT 2024Work plan drafted and shared at a high-level and will continuously share over the list and on future calls.14 OCT 2024
017Plenary Meeting #002 | 14 OCT 202414 OCT 2024ICANN org to share a high-level engagement plan outlining opportunities for the review team to communicate their work.ICANN Org25 OCT 2024Engagement plan shared during the meeting and will continuously share over the list and on future calls. 14 OCT 2024
018Plenary Meeting #002 | 14 OCT 202414 OCT 2024Investigate the possibility of securing a room at ICANN81 for any members of the review team already traveling to Istanbul.ICANN Org18 OCT 2024Investigation completed. 14 OCT 2024
019Co-Chair Meeting #003 | 08 OCT 202422 OCT 2024

Provide Co-Chairs with Example Work Plan

ICANN Org22 OCT 2024Email sent to CoChairs with the Example Work Plan document attached. 22 OCT 2024
020Co-Chair Meeting #003 | 08 OCT 202422 OCT 2024

Schedule follow-up call to discuss Example Work Plan in more detail

ICANN Org23 OCT 2024Calendar invitations sent to CoChairs for a follow-up discussion.23 OCT 2024
023Co-Chair Meeting #003b Deliverables Discussion | 24 OCT 202424 OCT 2024

Present upcoming schedule and proposed changes for Plenary calls to the PHR Team.

Co-Chairs / ICANN org28 OCT 2024Co-Chairs presented calendar and proposition for calls for the rest of the year.28 OCT 2024
024Plenary Meeting #003 | 28 OCT 202428 OCT 2024

ICANN org to post PPT (click here) from today's session.

ICANN Org28 OCT 2024File uploaded and posted on Wiki meeting space28 OCT 2024
026Plenary Meeting #003 | 28 OCT 202428 OCT 2024

Compile resources with a specific focus on Deliverable #4 and Deliverable #2 (Group #1) and send to the PHR Team members in advance of the next Plenary Call

ICANN org

11 Nov 2024

Email to the Pilot Holistic Review Team with the CIP Framework with highlighted sections of pertinence for Deliverables #4 and #2.10 NOV 2024
027Plenary Meeting #003 | 28 OCT 202428 OCT 2024

Review provided materials and come prepared to discuss potential approaches  deliverables #4 and #2

Pilot Holistic Review Team

18 Nov 2024

Pilot Holistic Review Team met on 18 NOV 2024 with a heavy dialog on the CIP workings and framework and the overlap with the PHR. 18 NOV 2024
028Plenary Meeting #003 | 28 OCT 202428 OCT 2024

Update PHR calendar invitations for the remainder of the year

ICANN org

28 Oct 2024

Rescheduling of calendar invitations sent across the list.28 Oct 2024
029Co-Chair Meeting #004 | 04 NOV 202404 NOV 2024

Schedule a follow-up call for 06 NOV

ICANN org04 NOV 2024Calendar invitations sent for 06 NOV to Co-Chairs04 NOV 2024
030Co-Chair Meeting #004 | 04 NOV 202404 NOV 2024

Determine areas of the CIP Framework for the PHR Team to focus on to inform the discussion on Deliverables #4 and #2


Co-Chairs / ICANN org11 NOV 2024Email to the Pilot Holistic Review Team with the CIP Framework with highlighted sections of pertinence for Deliverables #4 and #2.10 NOV 2024
031Co-Chair Meeting #004b | 06 NOV 202406 NOV 2024

Prepare slides to support the team’s discussion on deliverables #4 and #2.

ICANN org

18 NOV 2024

PPT deck for the next PHR Plenary call created.12 NOV 2024
032Co-Chair Meeting #004b | 06 NOV 202406 NOV 2024

Circulate the CIP Framework to the PHR team for review.

ICANN org

13 NOV 2024

Email to the Pilot Holistic Review Team with the CIP Framework with highlighted sections of pertinence for Deliverables #4 and #2.10 NOV 2024
034Plenary Meeting #004 | 18 NOV 202418 NOV 2024Ensure PPT decks from past meetings are posted on the Wiki.

ICANN org

19 NOV 2024All Plenary Meeting spaces have PPTs included. 18 NOV 2024
035Co-Chair Meeting #005 | 19 NOV 202419 NOV 2024Develop a paper to outline the issues noted in the ATRT3 Final Report.ICANN org27 NOV 2024Draft of Examination of ATRT3 Recommendation 3.5 sent to Co-Chairs for review.02 DEC 2024
036Co-Chair Meeting #005 | 19 NOV 202419 NOV 2024Post proposed PPT slides before each plenary meeting.

ICANN org

OngoingPPT will be posted on Wiki spaces as soon as possible.Ongoing
037Co-Chair Meeting #006 | 03 DEC 202403 DEC 2024Revise staff paper examining ATRT3 Recommendation 3.5.

ICANN org

03 DEC 2024Revised staff paper sent to Co-Chairs for review.03 DEC 2024
038Co-Chair Meeting #006 | 03 DEC 202403 DEC 2024

Review updated staff paper and share with Pilot Holistic Review Plenary.

Co-Chairs

05 DEC 2024

Email sent to Plenary group from Co-Chairs with a summary and the staff paper attached. 04 DEC 2024
039Plenary Meeting #05 | 9 DEC 20249 DEC 2024Create a document to enable team members to express their position on the core elements of the Holistic Review and pose additional questions as needed.ICANN org13 DEC 2024Document designed toto determine the team’s alignment on the foundational elements of the Holistic Review – purpose, scope, and input shared with Co-Chairs.12 DEC 2024
040Co-Chair Meeting #007 | 17 DEC 202417 DEC 2024Revise the questions for the PHR Team and send to the Co-Chairs for final review.

ICANN org

18 DEC 2024Co-Chairs received updated questionnaire for review. 18 DEC 2024
041Co-Chair Meeting #007 | 17 DEC 202417 DEC 2024Develop a survey to better support the collection and analysis of PHR Team responses.

ICANN org

20 DEC 2024Finalized questions converted to a survey. 20 DEC 2024
042Co-Chair Meeting #007 | 17 DEC 202417 DEC 2024Send the survey to the PHR Team members.

ICANN org

20 DEC 2024Invitations to the survey sent to the PHR Team members.20 DEC 2024
043Co-Chair Meeting #008 | 16 JAN 202416 JAN 2025ICANN org to coordinate communication between the Co-Chairs and GDS SVP.

ICANN org

16 JAN 2025
16 JAN 2025
044Co-Chair Meeting #008 | 16 JAN 202416 JAN 2025Invite Cheryl Langdon-Orr and Pat Kane to next plenary call to clarify on the PHR objective regarding the review of SO/AC/NC as a whole.

ICANN org

17 JAN 2025Email communication sent to ATRT3 Co-Chairs.17 JAN 2025
045Plenary Meeting #006 | 22 JAN 202522 JAN 2025Organize a working session with the OEC and relevant PHR members to discuss the PHR’s current status, and the Board’s expectation for PHR work.

ICANN org

03 FEB 2025Informational session with the OEC scheduled.03 FEB 2025
046Plenary Meeting #006 | 22 JAN 202522 JAN 2025PHR members report back to the team on discussion with the Organizational Effectiveness Committee.

León Sánchez

03 FEB 2025CoChairs gave update on discussions with OEC members during Plenary Call.18 FEB 2025
047Co-Chair Meeting #009 | 28 JAN 202428 JAN 2025

Cancel next PHR plenary call and send a request to the PHR Team to discuss “good practices” over the email list.

Co-Chairs

29 JAN 2025

Meeting cancelled and discussion started over list.29 JAN 2025
048Co-Chair Meeting #010 | 11 FEB 202511 FEB 2025

ICANN org to draft agenda and slide deck for 19 February PHR Plenary Call.

ICANN org

14 FEB 2025Presentation drafted and shared during 19 February sessions. 14 FEB 2025
049Co-Chair Meeting #010 | 11 FEB 202511 FEB 2025

ICANN org to draft a summary of the PHR Co-Chairs discussion with the OEC that includes proposed next steps and a requested meeting with SO/AC Leadership and the OEC.

ICANN org

12 FEB 2025Summary completed and collaborating with Policy to request SO/AC Leadership meeting with the OEC. 14 FEB 2025