When: Monday, 27 August 10 September 2012. GMT Standard Time. 19:00 UTC / This is a 90 Minute Call.
...
- Agenda Bashing (2 Min)
- Review Previous Week Action Items (10 0 Min)
- All Open Actions Reviewed & Closed
- Review Implementation Plan of Survey (70 80 Min)
- New Business (5 Min)
- Review of Assigned Action Items (3 Min)
Open Action Items:
- 20 Aug - Wilson - Make changes to survey tool outline in Review ToolRefer to milestone schedule below
Current Key Milestones:
- Complete LimeSurvey hosting implementation on ICANN web servers – 27 August 2012 - COMPLETE
- Migrate draft survey from ISOC server to production – 31 August 2012
- Update survey with changes outlined in public comment review tool – 31 August 2012
- Integration Test by WG – 7 10 September 2012
- Implement Survey Communication strategy – 7 10 September 2012
- Submit to GNSO & release survey for 30 days – 7 September 2012– 11 September 2012 (close 31 October 2012)
- Review Survey results – Oct Nov 2012
- Release Survey results – 30 Oct Nov 2012
- Publish Final Report – 30 Nov – 21 Dec 2012