The scope of work for this review includes years from 2011 to the present. Any additional areas of exploration during the review are dependent on input from the ICANN Board’s Organizational Effectiveness Committee (OEC) and/or the SSAC Review Work Party. In addition, the SSAC may perform a self-assessment in preparation for, or in parallel with, the independent examiner’s work.


Timeline

October 2017 February 2018 - Work plan + timeline

October 2017 March 2018 - Interview plan

November 2017 March - April 2018 - Survey(s) plan

October 2017 – March 2018 - June 2018 - Conduct Independent Review - Deliver Assessment Report; solicit feedback

April September 2018 - Deliver Draft Final Report; solicit feedback

June November 2018 - Deliver Final Report; solicit feedback 

...