Timeline


September - Start Review*

September - Work plan + timeline

September - Initial Meeting (via conference call) with RSSAC Review Working party

September - Interview plan

In-person: RSSAC October Workshop (subject to RSSAC approval), ICANN60, remote: as needed - Interviews conducted

October - Survey(s) plan

Prior to ICANN60: remain open for ≥30 days - Survey goes online*

28 Oct- 3 Nov 2017 - ICANN60*

January 2018 - Deliver Assessment Report

January / February 2018 - Public Consultation, e.g. webinar*

10-15 March 2018 - ICANN61*

March 2018 - Deliver Draft Final Report

April 2018 - Public Comment (run by ICANN)

June 2018 - Deliver Final Report

* fixed dates