- The GNSO Council approves this Project Change Request.
- The GNSO Council instructs policy support staff to update the TPR charter accordingly and post the updated charter on the GNSO’s website and Working Group wiki.
Approval of a Project Change Request (PCR) to Extend the Project Timeline of the EPDP on Specific Curative Rights Protections for IGOs
Submitted by: John McElwaine
Seconded by:
Whereas,
- On 19 August 2021, the GNSO Council initiated an Expedited Policy Development Process (EPDP) on Specific Curative Rights Protections for Intergovernmental Organizations along with its charter;
- The EPDP Team published its Initial Report for public comment on 14 September 2021;
- The EPDP Team received thirty-three comments from 14 individuals, 13 Organizations, and 6 community groups;
- The EPDP Team has determined that the substantive nature of the comments will require additional time to thoroughly review in addition to the remaining tasks to prepare a Final Report;
- The EPDP leadership team has submitted a Project Change Request outlining the full rationale for extending the project timeline.
Resolved,
- The GNSO Council approves this Project Change Request.
- The GNSO Council instructs policy support staff to update the EPDP Team’s project plan and other materials accordingly and post them on the EPDP wiki project space.